June 2023
Construction Update

play
volume
pause

June 2023
Construction Update

The heart of South Bank  
breaks ground

Marking another milestone in the development of our island resort, the Clubhouse has officially broken ground. Forming the heart of the amenities lining the shore of the Lagoon, the resort lobby, restaurant and bar areas have followed in the footsteps of the Gym and Spa buildings, which are already well underway. We are pleased to share a first glimpse of some new renderings with you that reveal the updated vision designed by Blee Halligan and our interior design partners for the public spaces, Thurstan Design from London. 

Operated by Grace Bay Resorts, the restaurant and bar will elegantly yet casually spill from the courtyard onto a lagoon beach deck providing a combination of covered and uncovered dining and lounging spaces.

With the Clubhouse scheduled for completion in Q1 2024, the full resort operation at South Bank will commence. Staff hiring is already in full swing.

  • LAGOON
  • ARRIVAL_SMALL
  • June 2023 Construction Update
  • June 2023 Construction Update

Final phase of construction at
The Lagoon

At the Lagoon, while the Gym and Spa are coming alive and bringing shape to the final vision of this vibrant neighborhood, the last stretch of the Lagoon Villas is close to completion with only five villas to be handed over to owners over the next 8 weeks. The Lagoon will be the first South Bank neighborhood to be realized. 

  • June 2023 Construction Update
  • June 2023 Construction Update
  • June 2023 Construction Update
  • June 2023 Construction Update
  • June 2023 Construction Update

Arc’s Architect, Piero Lissoni greets
owner’s in NYC 

It was fantastic to see some of you at Arc’s cocktail evening, A celebration of Design in collaboration with Italian design houses Salvatori and Boffi DePadova. We very much enjoyed sharing the creative vision of Arc with you directly from the renowned design minds of Lissoni and Partners, and it was a joy for us to see the excitement about the concept of Arc. Thank you to Chef Michele Casadei Massari for his delectable canapés and aperitivos showcased in his live culinary performance. Featuring products and finishes selected by Piero Lissoni for Arc, the showrooms of Salvatori and Boffi DePadova set the ideal backdrop for the lovely occasion.

June 2023 Construction Update

June 2023 Construction Update

Update for Launch and
Ocean Estate homeowners

Construction of the Ocean Estate villas and the Boathouses is progressing swiftly with first and second floor structures of just about all villas well visible now. Unfortunately, we are still being challenged by delays caused by global shipping, sourcing and availability delays of finish items and electrical supplies. All parties involved are working tirelessly to ensure the homes are delivered as soon as possible. By the end of the year, we anticipate completing Boathouse buildings D and E, as well as at least half of the Ocean Estate villas. We will maintain our priority to continuously update each owner about their completion schedule as information becomes available to us through the rest of this year.

Please understand that we will not be able to accommodate owner variations to villas at this point moving forward without causing more significant delays.